| Activity Name | Type | Qty / Unit | Unit Cost | Direct Cost | Start / End | Status | Flagged | |
|---|---|---|---|---|---|---|---|---|
| Foundations2 activities | $111,000 | Jul 15, 25 → Aug 28, 25 | Active | |||||
Foundation Slab – Zone A | foundation slab | 320 m3 | $185 | $59,200 | Jul 15, 25 → Aug 5, 25 | Active | ||
Foundation Slab – Zone B | foundation slab | 280 m3 | $185 | $51,800 | Aug 6, 25 → Aug 28, 25 | Pending | ||
| Structural Frame3 activities | $101,050 | Aug 20, 25 → Oct 20, 25 | Pending | |||||
Ground Floor Columns | column | 48 m3 | $420 | $20,160 | Aug 20, 25 → Sep 10, 25 | Pending | ||
Level 1 Beams & Slab | beam | 110 m3 | $395 | $43,450 | Sep 11, 25 → Oct 5, 25 | Pending | ||
Level 2 Columns (flagged) | column | 48 m3 | $780 | $37,440 | Oct 1, 25 → Oct 20, 25 | Pending | ⚠️ Price Outlier | |
| Fit-Out & Finishes3 activities | $461,500 | Oct 10, 25 → Feb 28, 26 | Pending | |||||
Interior Partition Walls – L1 | light wall | 1,450 m2 | $38 | $55,100 | Oct 10, 25 → Nov 20, 25 | Pending | ||
Interior Paint – All Floors | paint | 8,200 m2 | $12 | $98,400 | Dec 1, 25 → Jan 15, 26 | Pending | ||
Gypsum Ceilings – All Units | gypsum ceiling | 5,600 m2 | $55 | $308,000 | Jan 20, 26 → Feb 28, 26 | Pending | ||