Procurement

Purchase orders & approvals

Total PO Value

$115,520

2 orders

Pending Approval

1

Awaiting sign-off

Approved & Ordered

0

Active procurement

Overdue Approvals

2

Action required

Purchase Orders

Click a row to see line items
PO #ActivitiesLinesTotal CostStatusDue DateCreatedAction
PO-001OVERDUE
Foundation Slab – Zone A5$84,320
Pending Approval
Jul 8, 2025Jun 12, 2025
PO-002OVERDUE
Ground Floor Columns3$31,200
Draft
Aug 10, 2025Jun 14, 2025

Rules Engine Alerts

4
PO-001 Approval OverdueOverdue Approvalpo-001

Purchase Order PO-001 ($84,320) for Zone A slab materials requires approval by Jul 8. Activities start Jul 15 — procurement lead time at risk.

Created Jun 13, 2025

Column Unit Price Outlier – Level 2Price Outlieract-008

Activity "Level 2 Columns" has a unit cost of $780/m3 vs. standard $420/m3. This is an 86% deviation from recipe-based pricing. Please verify.

Created Jun 12, 2025

Rebar Stock InsufficientMissing Stockmat-rebar

Rebar needed for acts 001–003 totals ~50 ton. SteelFirst has 120 ton available but lead time is 7 days — order must be placed by Jul 8 to meet Zone A start.

Created Jun 14, 2025

Cement Stock Low at BuildMatLow Stockmat-cement

BuildMat Warehouse has only 4,000 bags of cement. Total cement needed for acts 001–002 is 4,320 bags. Split order with CementPro recommended.

Created Jun 14, 2025