Riverside Mixed-Use Block C

Meridian Development Corp.

Tel Aviv, ILJul 1, 2025Mar 31, 2026$4,800,000 budget

Total Budget

$4,800,000

Project proj-001

Activities

11

2 active

Active Alerts

4

1 critical

Pending PO Value

$84,320

Awaiting approval

Weekly Material Cost Demand

Estimated procurement spend by ISO week

Active Alerts

4 unresolved

4
critical

PO-001 Approval Overdue

Purchase Order PO-001 ($84,320) for Zone A slab materials requires approval by Jul 8. Activities start Jul 15 — procurement lead time at risk.

warning

Column Unit Price Outlier – Level 2

Activity "Level 2 Columns" has a unit cost of $780/m3 vs. standard $420/m3. This is an 86% deviation from recipe-based pricing. Please verify.

warning

Rebar Stock Insufficient

Rebar needed for acts 001–003 totals ~50 ton. SteelFirst has 120 ton available but lead time is 7 days — order must be placed by Jul 8 to meet Zone A start.

info

Cement Stock Low at BuildMat

BuildMat Warehouse has only 4,000 bags of cement. Total cement needed for acts 001–002 is 4,320 bags. Split order with CementPro recommended.

Recent Activities

11 total work items

1 flagged for review
NameTypeQty / UnitStatusStart Date
Foundations
group0 activeJul 15, 2025
Foundation Slab – Zone A
foundation slab320 m3activeJul 15, 2025
Foundation Slab – Zone B
foundation slab280 m3pendingAug 6, 2025
Structural Frame
group0 pendingAug 20, 2025
Ground Floor Columns
column48 m3pendingAug 20, 2025
Level 1 Beams & Slab
beam110 m3pendingSep 11, 2025
Level 2 Columns (flagged)
column48 m3pendingOct 1, 2025
Fit-Out & Finishes
group0 pendingOct 10, 2025
Interior Partition Walls – L1
light wall1,450 m2pendingOct 10, 2025
Interior Paint – All Floors
paint8,200 m2pendingDec 1, 2025
Gypsum Ceilings – All Units
gypsum ceiling5,600 m2pendingJan 20, 2026